Nimbus Expense: Multi-Currency & Delegate Approvals

TPM Command Center — as of 2026-08-14

Executive Summary

REDLIKELY LATE

The Aug 14 status check rates the project **RED**: the critical path has already slipped one business day, moving the finish from 2026-08-20 to 2026-08-21. The independent Monte Carlo forecast corroborates that exact date at the 50th percentile — two different methods, the same number — but it also localizes the residual risk more precisely than the status report alone does: Platform Eng, the team whose task started the slip, is now forecast comfortably **on track** on its own remaining work, while the real tail risk sits with **Backend Eng**, whose most recent sprint came in well under its trailing average. Their 95th-percentile forecast finish, 2026-08-24, is three days later than the status report's revised date — the number worth watching isn't the one already in the RAG report, it's this one.

Backlog

Epics
5
Tasks
23
Story points
78
EpicPriorityTasksPoints
EPIC-1 — Multi-currency expense submission & displayHigh828
EPIC-2 — Shared approval-resolution engine & delegate setupHigh522
EPIC-3 — Delegate notifications & audit trailMedium413
EPIC-4 — Admin controls for rolloutMedium37
EPIC-5 — Finance reporting export updatesMedium38

Critical Path

Planned finish: 2026-08-20

TaskTeamStartFinish
EPIC-2-1 — Build shared approval-resolution service for normal and delegate routingPlatform Eng2026-08-032026-08-11
EPIC-2-3 — Store delegation records with auto-expiry at end of date rangeBackend Eng2026-08-112026-08-14
EPIC-3-4 — Extend notification service for delegation lifecycle eventsPlatform Eng2026-08-142026-08-20

Status Highlights

The critical path has already slipped: EPIC-2-1 (zero slack) finished one business day late on Aug 12, and EPIC-2-3 (also zero slack) is now confirmed one day behind as a result, with Backend Eng stating there's no way to compress it further. Absent a decision to compress EPIC-3-4, the project finish moves from 2026-08-20 to 2026-08-21. Overall status reflects this — the worst-rated load-bearing epic — even though the slip is one day and one open risk (the compliance question on export attribution) was resolved this period.

SeverityRiskOwnerAsk
HIGHCritical path has slipped 1 business day (EPIC-2-1 → EPIC-2-3), with no compression available on the Backend Eng side.Platform Eng / Backend EngConfirm whether to accept the 1-day slip to 2026-08-21, or authorize parallel/expedited work on EPIC-3-4 to try to hold the original 2026-08-20 date.
MEDIUMFX integration (EPIC-1-2) burned half its schedule buffer resolving a vendor rate-limit issue; only 1 day of slack remains if it recurs.Backend EngNo action needed yet — flagging so it isn't a surprise if this needs escalation next period.
MEDIUMEPIC-3-4 hasn't started and the whole revised finish date depends on its 4-day estimate holding exactly, with zero slack to absorb any further surprise.Platform EngNone currently — monitoring. Will escalate if EPIC-2-3 slips past Aug 15.

Slippage Forecast

Planned finish 2026-08-20 — P50 2026-08-21, P85 2026-08-21, P95 2026-08-24.

TeamRemaining ptsP50P85P95RiskLoad-bearing
Backend Eng132026-08-212026-08-212026-08-24LIKELY LATEYes
Platform Eng52026-08-192026-08-192026-08-19ON TRACKYes
Finance Eng32026-08-182026-08-182026-08-18ON TRACKNo
Web Eng82026-08-192026-08-192026-08-19ON TRACKNo
Mobile Eng02026-08-142026-08-142026-08-14ON TRACKNo