As of 2026-08-14
REDThe critical path has already slipped: EPIC-2-1 (zero slack) finished one business day late on Aug 12, and EPIC-2-3 (also zero slack) is now confirmed one day behind as a result, with Backend Eng stating there's no way to compress it further. Absent a decision to compress EPIC-3-4, the project finish moves from 2026-08-20 to 2026-08-21. Overall status reflects this — the worst-rated load-bearing epic — even though the slip is one day and one open risk (the compliance question on export attribution) was resolved this period.
| Epic | Status | Notes |
|---|---|---|
| EPIC-1 — Multi-currency expense submission & display | AMBER | EPIC-1-2 (FX rate integration) finished, but consumed half its schedule buffer (2d slack down to 1d) resolving a vendor sandbox rate-limit issue. No confirmed slip yet, but the remaining buffer is thin. |
| EPIC-2 — Shared approval-resolution & delegate setup | RED | EPIC-2-1 (zero slack, on critical path) finished 1 business day late (Aug 12 vs. planned Aug 11) due to an unplanned permissions issue with the Identity team. EPIC-2-3 (also zero slack) started a day late as a result and is now projected to finish Aug 15, one day past its Aug 14 target, with Backend Eng saying they're already at capacity and can't compress further. |
| EPIC-3 — Delegate notifications & audit trail | AMBER | EPIC-3-4 (zero slack, on critical path) hasn't started yet — blocked on EPIC-2-3. Platform Eng's own 4-day estimate is unchanged, so once unblocked this shouldn't add further delay beyond the 1 day already reflected in the project finish date, but the entire finish date now rides on that estimate holding exactly. |
| EPIC-4 — Admin controls for rollout | GREEN | All admin/rollout work is low-risk and off the critical path with wide slack; no issues reported. |
| EPIC-5 — Finance reporting export updates | GREEN | The compliance question this whole epic was gated on has been resolved, and the remaining work (EPIC-5-3) is now unblocked with its slack intact. |
| Severity | Risk | Owner | Ask |
|---|---|---|---|
| HIGH | Critical path has slipped 1 business day (EPIC-2-1 → EPIC-2-3), with no compression available on the Backend Eng side. | Platform Eng / Backend Eng | Confirm whether to accept the 1-day slip to 2026-08-21, or authorize parallel/expedited work on EPIC-3-4 to try to hold the original 2026-08-20 date. |
| MEDIUM | FX integration (EPIC-1-2) burned half its schedule buffer resolving a vendor rate-limit issue; only 1 day of slack remains if it recurs. | Backend Eng | No action needed yet — flagging so it isn't a surprise if this needs escalation next period. |
| MEDIUM | EPIC-3-4 hasn't started and the whole revised finish date depends on its 4-day estimate holding exactly, with zero slack to absorb any further surprise. | Platform Eng | None currently — monitoring. Will escalate if EPIC-2-3 slips past Aug 15. |